Consumer Unit Upgrade
Electrical • Leeds LS1 • Posted 2 Jul
Looking for tradesmen
This job is open for quotes from local tradespeople.
Description
Old fuse box needs upgrading to a modern consumer unit with RCBOs. Three-bed semi, loft conversion already wired.
Timeline
Within 1-2 weeks
Budget
£500 – £1,000
Price breakdown & estimate
A guide price split for this job. This is not the live work plan — tradespeople set the real price when they quote.
Indicative estimate · Larger project
£500 – £1,000
Matched to the budget range on this job.
- 1
Survey & circuit design
~£75Inspect consumer unit, plan circuits and confirm load.
10% · approx 1 day
- 2
First fix wiring
~£300Run cabling, back boxes and containment.
40% · approx 3-4 days
- 3
Second fix & terminate
~£263Fit accessories, terminate and energise circuits.
35% · approx 2 days
- 4
Test & certify
~£112Inspection, testing and EIC certificate issued.
15% · approx 1 day